Estimated End Date
August 31, 2023
Address
7000 College Way, Coldstream
Budget
$418,000
Funding Source
Community Works Funds and General Revenue
Participating Community
Area B
Area C
City of Vernon
District of Coldstream
Status
Completed
Project Description
Through the UBCM Canada Community Building Fund, Community Works Funds are provided to local governments for local infrastructure and capacity-building projects. This project will be funded through Community Works Funds for $238,000, and General Revenue for the remaining.
The Greater Vernon Athletics Park is utilized by residents, sports groups and visitors for sports programs, recreational activities, and events. This project will see improvements to the including:
- repaired netting on hammer cage
- paved portion of the shot put area
- replacement of football goalposts
- perimeter path repaving
- track line repainting
Timeline
Hammer Cage Netting
Complete
Yes
Paved Shot Put Area
Complete
Yes
Track Line Painting
Complete
Yes
Replacement of Goal Posts
Target Completion Date
Complete
No
Perimeter Pathway Re-Paving
Target Completion Date
Complete
No
Contact Information
Department Contact