Mabel Lake Sewer - Generator Project

Mabel Lake Sewer - Generator Project3476 Mabel Lake Place, Mabel Lake, BC
Leaflet Map data © Google
Estimated Start Date
Fall 2021
Estimated End Date
Fall 2024
Address
3476 Mabel Lake Place, Mabel Lake, BC
Budget
$245,000
Funding Source
Community Works Funds
Participating Community
Area F
Status
Active

Project Description

The Regional District of North Okanagan (RDNO) manages the Mabel Lake Water (MLW) system located in Electoral Area “F”. The MLW system serves over 320 customers in the Kingfisher area, east of Enderby, as well as the Mabel Lake Campground.

The Mabel Lake Sewer area experiences frequent power outages, which results in the effluent at the lift station being directed to an overflow chamber that does not have treatment capabilities.  This project will see the installation of a standby power generator to allow the system to operate during a power outage and avoid the need to use the overflow chamber. 

In addition, significant electrical upgrades are also being completed to meet the needs of the generator and bring the electrical up to current code.

This project is fully funded by Community Works Funds from Electoral Area “F”.

Additional Project Information

  • Why is the project timeline 2 years long?

The pre-design and cost estimates were completed in 2022 and revealed that additional funding was required to proceed. Additional funding was secured in 2022 through the Community Works Funds, allowing us to move forward. Additionally, generators have long delivery timeframes, so the generator was ordered as soon as the funding was approved but delivery is not expected until fall 2023.

Timeline
Cost Estimate
Completion date
Pre-Design
Completion date
Funding Secure
Completion date
Generator Ordered
Completion date
Final Design
Target Completion Date
Complete
No
Construction Begins
Target Completion Date
Complete
No
Electrical Upgrades
Target Completion Date
Complete
No
Generator Delivered
Target Completion Date
Complete
No
Construction Complete
Target Completion Date
Complete
No
Commissioning
Target Completion Date
Complete
No