Estimated Start Date
April 8, 2024
Estimated End Date
May 17, 2024
Address
East Vernon Road
Budget
$237,741.40
Participating Community
Area C
Status
Completed
Project Description
The project consists of:
1. 105m of 150mm & 100mm diameter PVC C900 watermain and associated fittings;
2. 23m of 100mm diameter DR11 HDPE Water Service (install by HDD);
3. One Combination ARV and manhole, and one meter and backflow preventer and chamber and;
4. Approximately 95sq.m of asphalt driveway restoration.