Estimated Start Date
April 8, 2024
Estimated End Date
October 4, 2024
Address
Shantz Road from 11 Street East Towards Francis Street
Budget
$381,125.46
Participating Community
Area C
Status
Completed
Project Description
The project consists of:
1. 600 sq.m of asphalt removal and replacement
2. 570m of 150mm diameter PVC C900 watermain and associated fittings
3. 9 water services (25mm - 50mm diameter)
4. 1 fire hydrant
Timeline
Complete
No